State of CT/City of Hartford Economic Development Authority
Central Plant Development for Adriaen's Landing Project
SourceOne has served as the strategic advisor to the State and Municipal developers of the $750 million Adriaen’s Landing Project. The Adriaen’s Landing site is a 30-acre parcel that will ultimately accommodate Hartford’s new 220,000-square-foot convention center, a 400-room hotel, and 250,000 square feet of mixed use development with residential units, entertainment venues, and retail district. SourceOne was tenanted to support three primary elements of the project: technical review, financial evaluation, and contract development.
SourceOne’s technical and economic evaluation of the project concept plan entailed review and analysis of equipment selection, space allocation, preparation of a CUP proforma, and development of facility load profiles. SourceOne analyzed alternative supply concepts inclusive of third party supply from a proximate district chilled supply system in the downtown Hartford area. SourceOne serves as the lead State of Connecticut/City of Hartford Economic Development Authority negotiator with the hotel and convention center developers leading to the finalization of supply contract terms and conditions.
Contact
Tim Shea
Project Director
50 Columbus Boulevard ~ Suite 400
Hartford, Connecticut 06106
(860) 527-0100
Project Metrics
1,100,000 square feet
Peak Electric: 5 MW
Annual Electric: 18,000,000 kWh
Peak Thermal: 20,000 lbs/hr
Annual Thermal: 40,000 Mlbs
Peak Cooling: 2,500 Tons
Annual Cooling: 2,400,000 Ton/hrs
Project Capital: $750 million